Yellowstone’s Northeast Entrance: Riprap, Repairs, and Reconstruction

I

Yellowstone National Park’s Northeast Entrance Road (Tower Junction to the Northeast Entrance in Cooke City/Silver Gate, Montana) will open to regular visitor vehicle traffic Saturday, Oct.15 at 8 a.m. Reopening this section effectively opens “99% of the park’s roads,” officials state.

To put it bluntly, the National Park Service’s reconstruction efforts (along with Oftedal Construction, the Federal Highway Adminstration, and funding from the Emergency Relief for Federally Owned Roads) have been nothing short of heroic.

Today marks four months since the flooding in July.

Superintendent Cam Sholly surveys the road

Reconstruction efforts were surveyed this morning, October 13th, 2022, with the help of  Superintendent Cam Sholly, Public Information Specialist Linda Veress, Project Manager and Landscape Architect Doug Madsen, and Construction Control Inspector Brian Lamoreaux.

“I’ve never seen this level of coordination and collaboration in such a short amount of time, getting so much done,” Sholly says.

The Northeast Entrance Road has remained closed since the historic flood event in June, which caused significant damage to approximately five sections of the road. That will change this Saturday with efforts fully underway to open the entrance.

While riding to the construction sites with Ms. Veress, she outlines her journey with the National Park Service (NPS), which started with a summer job in college. “I got a job at Yosemite, that’s where I started,” Veress says.

After graduating from college, Veress decided to stay with NPS moving from park to park for a time – usually West of the Rockies. She’s been in Yellowstone for eight years. Currently, as the Public Information Specialist, she handles a wide and, at times, bizarre set of questions from the public.

 

“I never know what I’m going to find. My first email, seriously, on Tuesday – after the holiday – the first email I opened in the morning was about aliens,” Veress says. The person who emailed Veress was not talking about “illegal aliens,” they were asking about extraterrestrial life forms.

“They were asking about aliens on federal lands, so, you never know,” Veress says humorously. “And then there was a time, I don’t know, a few years ago, somebody sent me a video and wanted us to confirm that it was a family of Bigfoot – Bigfeet – at Old Faithful in the winter,” Veress explains.

At this time, Yellowstone National Park can neither confirm nor deny the presence of “Bigfoot.” Although, Veress says she told the folks inquiring about Bigfoot, “it might have been snowmobilers.”

Northeast Entrance Yellowstone reconstruction efforts

 

Cooke City residents use the Northeast Entrance for travel as it is the only road that’s open all winter long. In October, all the roads in the interior of the park (Canyon Village, Old Faithful, West Yellowstone, South to Jackson, etc.) close during colder months.

Discussing road damage from the floodwaters, Superintendent Sholly says, “the riprap wall they built…what we’ve found is that the areas of the corridor that had riprap were unaffected by the flood.”

Riprap, also known as “rock armor,” is human-placed rock or rubble used to protect shoreline structures against water and ice erosion. Riprap is commonly made from granite and modular concrete blocks.

Additionally, riprap impacts the amount of organic material in a waterbody by acting as a filter, often catching wood and leaves before they can enter the water.

Superintendent Cam Sholly

“As we look forward, I think it’s going to be important to think about what other sections of road in this corridor could be vulnerable to future flood events,” Sholly says.

Referring to riprap, Sholly says, “this is a proven technique to protect the corridor.” Sholly and his crew also note how the use of riprap is more cost effective than trying to divert the road further away from the river.

“Riprap, basically, it’s the larger boulders that you can see here, this is class 5 riprap. So, it’s actually averaging about three feet in length and width and height and the way this is placed, we’re actually four feet below the water line,” Blank Blank Brian Lamour says describing the technique.

“It’s been quite a process and definitely should withstand anything that’s thrown at it down the road,” Lamour adds. The crew approximates that the road was first built in the 1930s. Roads in Yellowstone undergo regular maintenance, but the road-base itself was quite old.

New pavement has gone down on sections of the Northeast Entrance as recently as “five days ago,” Sholly says. Given the labor to strengthen the roads, the engineers and officials believe the corridor will be better protected against future flooding.

Doug Madsen and Bob Campbell look over Trout Creek wash out

II

One major goal of reconstruction projects is to make them look “as natural as possible,” Sholly says. Natural debris and native materials constitute the bulk of the filler being incorporated in rebuilding. Design for reconstruction has received input from hydrologists, hydromorpologists, landscape architects, and engineers.

“Considering this is only four months ago, considering what this looked like and has looked like over the last couple months, it’s pretty impressive that it’s gotten back to this position so quickly,” Sholly states.

“It’s a total team effort,” Sholly adds. Reconstruction in this corridor has addressed issues with wastewater, damaged roads, turnouts, and a smattering of park operations.

Project Manager Doug Madsen explains that one of the difficulties for reconstruction in a corridor like this is the lack of facilities for construction. There are no large staging areas, those had to be created – even spots to turn around had to be established. Doug has spent twenty years in the park with environmental compliance.

Wildlife has also impacted reconstruction this fall. “We’ve had grizzlies walk through our work zone, and buffalo jams,” Lamoreaux says.

Project Manager and Landscape Architect Doug Madsen

With the river so close to the roads, engineers have made to push the water back to fortify and mend the damage. “In order to do construction, you have to move the water away. In this case, the water was where the road was. You would be relocating a road considerably if you weren’t going to deal with that water. And so, pushing it back, the Corps of Engineers gives us the ability to work and channel those rivers,” Madsen explains.

“They were very, very careful in how they did that,” Sholly notes. Roughly “300,000” tons of material had to be moved in order to assist with repairs and realignments. Again, these native materials were pulled from the surrounding areas, any materials that had to be brought in from outside the park were cleaned and treated.

“We brought in a lot of the road-base that goes under the pavement. There’s about eight inches of gravel that gets compacted under the asphalt to give it more strength,” Madsen says. The Trout Creek area suffered “600 feet of length” in road loss. Many of the original roads in Yellowstone were old wagon roads and so throughout the years layers of oiled gravel and asphalt make up the roads people use in the park today. Current reconstruction efforts will dramatically increase the toughness and resiliency of the corridors – more like the way a modern highway would be built.

Embankments near Pebble Creek bridge also had to be rebuilt.

Trout Creek wash out area

Superintendent Sholly, commenting on the Yellowstone’s 150th anniversary this year, says, “This is an important year…this year will be remembered largely because of the flood, but I think it’s important for people to understand that we a lot of important work on the 150th commemoration prior to the flood occurring and we got back on track pretty quickly.” Sholly mentions, despite the damage, many 150th goals were achieved, which includes increased numbers of tribal nations back in the park, complete projects on employee housing, and several transportation projects coming to a close now.

The collaboration between the states, governors, counties, members of Congress, the Department of the Interior, the Department of Transportation, the Federal Highway Administration,  and the two primary construction contractors has been remarkable, Sholly explains. The NPS knows they still have plenty of hard work left to do, and, admittedly, the crews are exhausted, but determined.

Despite Yellowstone’s herculean push to fix the flood damage, some residents of Cooke City have reported seeing a “50-70%” loss in revenue from the drop in tourism this summer.

“If you asked me June 13th when we started seeing these damage reports, and we were evacuating the park, and there was no power for forty hours, and 200,000 gallons of wastewater was dumping into the Gardiner River, if you asked me that point would we be standing here today four months later having the conversation that we’re having, and seeing the repairs done that we’re seeing, I would have probably said that was not feasible,” Sholly says.

Sholly credits his team and their partners with the speedy recovery that aims to reconnect communities in Gardiner, Silver Gate, and Cooke City. The opening  of the Northeast Entrance this Saturday represents a milestone in the Yellowstone’s flood recovery.

Superintendent Sholly, when asked whether there’s been anything particularly comical or frustrating during the recovery process, said, “People care about Yellowstone, and I think probably the most irritating set of comments we got was – and I understand it – when we evacuated the entire park. There was 10,000 visitors in the park in mid-June, and a lot of folks down south didn’t think that was necessary – that were staying in campgrounds and things like that – and I need to remind people that we started evacuating the northern loop first.”

Citing catastrophic damage, unsafe conditions, and wastewater failures,  Sholly stands by his decision to evacuate the park. “Some of the things people didn’t see was the Canyon wastewater system and the Old Faithful system were severely compromised during the flood event and that’s kind of an invisible part of this whole thing.” Even though the damage was less on the south loop, there was still damage, but it wasn’t as visible as the damage on the northern end of the park. NPS needed to make sure infrastructure was functional and could be relied on.

Referring to the evacuation of Yellowstone, Sholly says, “I think that it was one of the best decision we made early on.”

 

 

The post Yellowstone’s Northeast Entrance: Riprap, Repairs, and Reconstruction first appeared on Big Horn Radio Network | Wyoming.KODI News, LOCAL NEWS, National News, Wyoming News, Cam Sholly, Cooke City, Doug Madsen, Flood Recovery, Gardiner, Linda Veress, National Park Service, Northeast Entrance, Opening, Reconstruction, Riprap, Saturday, Silver Gate, Yellowstone National Park I Yellowstone National Park’s Northeast Entrance Road (Tower Junction to the Northeast Entrance in Cooke City/Silver Gate, Montana) will open to regular visitor vehicle traffic Saturday, Oct.15 at 8 a.m. Reopening this section effectively opens “99% of the park’s roads,” officials state. To put it bluntly, the National Park Service’s reconstruction efforts (along with Oftedal…
The post Yellowstone’s Northeast Entrance: Riprap, Repairs, and Reconstruction first appeared on Big Horn Radio Network | Wyoming. LOCAL NEWS | Big Horn Radio Network | Wyoming 

Related Articles

Newsletter Signup

KODI Authors